Newport
East (Nash) Wind Turbine
energy saving and efficient wind turbine powers innovation at a
South Wales WwTW
by Andrew Bowen, Paul Thacker & Stewart Bell
(published October 2018)
 |
 |
Installation of the first shaft section
Courtesy of Welsh Water |
Final shaft section being lifted into position
Courtesy of Welsh Water |
 |
 |
The first blade being lifted into position
Courtesy of Welsh Water |
The completed 127m tall wind turbine at Nash
Courtesy of Welsh Water |
Welsh
Water is committed to reducing its carbon footprint and
protecting the environment from the effects of climate change
and is pursuing measures to generate more of its own power from
renewable sources. Welsh Water recently signed a five-year
contract with Dong Energy to supply green energy to power its
sites, as well as introducing ways to reduce the energy use from
the National Grid from its operations. To help achieve this
outcome, Welsh Water sought planning permission to erect a
single 2.5MW wind turbine at the Nash WwTW sited at West Nash
Road, south east of the city of Newport. The turbine will
generate 6GWh annually, or around 6% of Welsh Water’s current
renewable electricity generation, delivering significant savings
through reduced power costs and via Renewable Obligation
Certificates (ROCs) income. The scheme forms part of Welsh
Water’s strategy to reduce the overall carbon footprint and
produce electricity to power its own assets, in the interests of
self-sufficiency and environmental sustainability.
The project
The project started in
April 2016 and was delivered by principal contractor Skanska.
The projects had two key targets:
-
To erect and operate the
turbine against an incredibly tight programme and ensure the
turbine was commissioned prior to the 31 March 2017.
-
To build on the
environmental and construction practises already demonstrated in
the project at Swansea Bay Wind Turbine.
At Nash WwTW, the turbine
was designed to generate around 6GWh per annum. When flow rates
into the WwTW are low It was anticipated that 37% of the power
generated would be exported to the grid and assist Welsh Water
achieve its 50% carbon reduction through renewables.
 |
Overview of the project and delivery of the final
turbine shaft section - Courtesy of Welsh Water |
Carbon footprint
A carbon footprint study
was undertaken on the project, which involved discussions with
the lead design team ARUP to produce a turbine base which would
be low in carbon.
The structural designs
for the turbine base had to meet industry practice design
criteria, which proved challenging with the ground conditions
present. Lewis Civil Engineering and piling contractor Skanska
Cementation requested concrete mixes (C45/55 and C32/40) which
included recycled content of at least 70% GGBS.
Ground conditions
The complex ground
conditions and engineering solutions required considerable
attention in the planning stages. The initial design was for a
monopile foundation, which was 11.2m in diameter and 30m deep
(2,955m3).
This required a caisson
shaft design, involving precast units and a concrete pour of
over 2955.61m3, in addition to the concrete required
for the plug and precast units. This was challenged by the
construction team and an alternative design was proposed by
Malachy Walsh & Partners (MWP). This met the needs of the
programme and required just 760m3 of concrete.
Llanwern steel works
required 400,000 tonnes of soil for a landfill restoration
project. Skanska engaged with the steel works to see if the soil
from the site would be suitable; it was and over 8,736 tonnes
was taken there, creating significant cost savings. This
approach was part of a wider strategy to try to make the scheme
as environmentally sustainable as possible.
 |
A Liebherr LTM 1500-8.1 laid down due to high winds -
Courtesy of Welsh Water |
Environmental
sustainability
Lewis Civil Engineering
procured low carbon concrete mixes, recycled aggregate and used
Tensar Geogrid. Using Tensar Geogrid reduced the amount of
excavation and infilling of materials required for the final
design of the pile mat and crane pad by 50%.
This lesson was learned
from the earlier turbine project at Swansea. The project
also identified opportunities to ensure materials used for the
temporary works (a piling platform and a crane pad) could be
reused as part of the permanent design after installation.
The team identified a
further opportunity to add biodiversity value to the WwTW,
through the sowing of a wildflower meadow. The diversity of
species in the grassland around the site of the turbine was
enhanced to create a wildflower grassland and foraging habitat.
The wildflower mix is specifically designed to provide maximum
food resource for pollinators and other insects. This measure
supports the Welsh Government’s Action Plan for Pollinators in
Wales (2013) to halt and reverse native pollinator decline in
Wales.
The scheme is currently
seeking Skanska’s Deep Green accreditation, similar to the
previous turbine installed at Swansea that achieved the
following targets:
Floating new ideas
The project brought about
considerable logistical challenges, with the movement of the
turbine itself being the principle one. The turbine had to be
delivered down the River Usk on a barge, before being
transported the short distance to the South Wales site. The use
of the river as a transport link saved considerably on
disruption to the local traffic, had the extra-long 50m blades
been transported by road on a lorry.
 |
The transport barge moored up at Uskmouth Power Station
- Courtesy of Welsh Water |
Site access
Components such as the
10-tonne rotor blades would have required escort riders and even
road closures to access the site by road through the village.
The alternative route was created especially for the project, to
deliver the 127m-tall wind turbine on site to Nash WwTW.
The project team
implemented a suitable construction and reinstatement plan and
carried out all the work associated with the delivery,
transportation and erection of the turbine. The access road that
was built to the turbine location went through Liberty Steel and
SIMEC Power Station and needed to be removed following
installation.
The access route required
considerable upgrading and modifying to accommodate the 50m long
transporter wagons. The road construction had to navigate across
two drainage channels (known locally as Reens), both of which
were heavily protected environmentally. These factors
collectively made the installation a complicated prospect at
several points in the project.
The road forward
Within the works, the
design team also considered the existing assets to be ‘at risk’,
so the project team overcame this by installing almost 1000m2
of protective concrete road surface. The complicated engineering
works resulted in the subcontractors working day and night to
prepare the site for piling works initially.
Following the completion
of the piling work, the site was then prepared for the formed
reinforced concrete (FRC) work at the wind turbine base, which
consisted of around 400m3 of concrete. With the FRC
completed, Lewis then installed over 14000 tonnes of recycled
aggregate to form a 1200m access road.
The site team working on
the concrete road deployed over 300 sheets of A393 mesh and
almost 300m3 of RC 40/50 concrete placed to protect
the existing assets. One challenge was the speed the work needed
to be carried out, to maintain continued access to the site. A
bespoke rapid-setting concrete was used, which was designed by
Lewis and its concrete supplier Cementation under the P450
description. This allowed curing to take place within 24 hours,
and tankers could drive safely on it within a day of it being
laid.
Lewis’s worked on the
project for 30 weeks, with the sub-contract valued at £1.27m+ as
part of the overall budget.
 |
Off loading the 47.8m turbine blade at the dock side -
Courtesy of Welsh Water |
Delivering the turbine
As the site was fully
prepared for the arrival of the turbine structure, an unforeseen
circumstance hastened a potential delay. At the docks where the
turbine was being stored, the crane broke down during the
loading of the barge with the crane components. This resulted in
the vessel missing the tide for the delivery slot.
When the components
arrived, the heaviest component had to be loaded on the port
side of the ship. But when the vessel arrived at the jetty near
Uskmouth Power Station, the starboard side of the barge was
closest to the quay. This resulted in most of the cargo being
unloaded, then a patient wait for high tide, so that the ship
could be repositioned to gain access to the remaining
components.
Despite these delays, the
turbine was erected, powered up and commissioned almost a week
before schedule.
Newport East (Nash) Wind
Turbine Project – Key Participants |
Principal contractor
|
Skanska UK |
CAT III check - wind
turbine foundation
|
Raymond Brown |
Wind turbine foundation
design |
Malachy Walsh & Partners |
Access road and
electrical design
|
ARUP |
Design checks on piling
platform
|
Skanska Technical
Services |
Civils |
Lewis Civil Engineering
Ltd |
Electrical installation |
SSE Enterprise
Contracting |
N100/2500 turbine
|
Nordex |
SCADA kiosk & platform
|
Bridges Electrical |
Piling
|
Skanska Cementation |
HV Switchgear
|
Hawker Siddeley
Switchgear |
Conclusion
Work was completed on the
turbine in June 2017. The Nordex N100/2500 turbine will provide
over half of the annual energy needed to operate the Nash works.
The construction of the
wind turbine at Nash has engendered many benefits:
-
It cements Welsh Water’s
aspiration for more energy to power its assets from renewable
sources.
-
The construction
processes were aligned to minimise its impact on the
environment.
-
Brings biodiversity
benefits not just to the local site, but across the wider
region. It will mean that the National Grid will not have to
build more assets (power stations and electricity sub stations
etc) that will encroach on greenfield sites and impact the
biodiversity present in those areas, because of future energy
demand by Welsh Water.
The wind turbine has been
performing well, with high availability maximising output from
the turbine.
The editor
and publishers would like to thank Andrew Bowen, Project
Manager with Skanska, Paul Thacker, Sub-programme Manager
with Welsh Water, and Stewart Bell, Head of Water Process
with Skanska, for providing the above article for
publication. |