Search
Nominate/Submit Case Studies
Job Board

Amiblu Norway AS

Gipsy Patch Lane (Bristol) Sewer Rehabilitation

Structural rehabilitation of man-entry GRP culvert relining project

Structural defects of the pipe - Courtesy of Matt Durbin Associates Ltd

Gipsy Patch Lane, Bristol is a main road forming part of a new Cribbs Patchway Metrobus route in South Gloucestershire. As part of an asset assesment programme a few years ago, a CCTV survey showed many defects throughout the length of the surface water culvert at Gipsy Patch Lane. The defective sections ran under the busy carriageway so, as an interim maintenance measure the local authority excavated a section of the road and installed a concrete slab over the pipe to protect it from further deterioration or collapse.

During heavy rainfall over the summer of 2020, the same pipe was found to have suffered structural defects and root ingress through open joints and connecting laterals resulting in localised blockages of up to 90%. A new man-entry survey showed the pipe beneath the concrete slab to be deformed.

Major works were already under way in the area to replace a railway bridge on Gipsy Patch Lane, so South Gloucestershire Council took the opportunity to make improvements to the sewer in conjunction with the Network Rail works to minimise disruption, which was further aided by lighter traffic due to the regulations set in place for Covid-19 pandemic.

Under the Council’s Climate Resilient Scheme, the task was to find and deliver a suitable solution before opening the road up to traffic and risking a pipe collapse; two options were considered; open-cut to replace the section of pipe or trenchless technology to reline the affected pipe with little disruption to the area.

First post-Brexit delivery of Amiblu pipes (January 2021)

First post-Brexit delivery of Amiblu pipes (January 2021)

Doug MacKay, Project manager, South Gloucestershire Council consulted with Julian Britton, Critical Sewers Manager, Wessex Water and Matt Durbin Associates; specialist confined space and GRP structural relining installer to determine the most efficient and economic technique. As with many suburban roads, Gipsy Patch Lane is laden with many services within the carriageway, so rehabiliatation of the existing pipeline through trenchless installation of 210m x DN800 structural GRP jacking pipe supplied by Amiblu was decided upon. As the contract was classed as emergency works, subject to time constraints and speed of execution the use of Amiblu’s GRP pipes meant that MDA were able to remove the need for costly over-pumping and install the pipes in live flows, whilst minimising their work area to a single lane closure for uninterupted access to local businesses.

During the installation of the initial contracted 210m, a further 70m section of the pipe downstream required attention, so MDA undertook the additional works saving additional costs and disruption at a later date.

Amiblu jacking pipes are often utilised in pipe rehabilitation projects such as this as they offer a high compressive strength and, compared with conventional materials, an improved hydraulic coefficient. The hydraulic analysis carried out for Gipsy Patch Lane showed no reduction in hydraulic performance and as the pipes are designed to offer a service life in excess of 150 years with minimal maintenance, the life expectancy of this asset is greatly improved.

(left) GRP pipe installation and (right) the completed relining - Courtesy of MDA Ltd

(left) GRP pipe installation and (right) the completed relining – Courtesy of MDA Ltd

Doug MacKay, Project Manager with South Gloucestershire Council, commented:

“For this project, the Council had concerns about the risk of potential pipe collapse under traffic loading. The fact that road was already under a full closure due to an adjacent project to replace an old railway bridge meant that timing was critical for this project. It was essential that the work had to be completed before the proposed re-opening of the carriageway. Additionally, there was a limit to the funds available through the Climate Resilience budget to complete the scheme. We worked very closely with MDA and our designers to review the site constraints, risks to programme delivery and budget constraints to determine the most appropriate remedial solution. I was grateful for the time, input and patience spent by MDA during this period to explain the construction process and provide answers to all our questions and concerns in advance of making the final decision on the preferred option.

Once the decision was made to proceed with the pipe-jacking option the process was relatively straight-forward and stress-free from the Council side of things. In the main this was down to the excellent communication, planning and execution of the works by MDA. Both projects were completed on-time, within budget and with minimal disruption to the public and businesses that rely on using Gipsy Patch Lane.”

Amiblu pipes require minimal site storage - Courtesy of MDA Ltd

Amiblu pipes require minimal site storage – Courtesy of MDA Ltd

Project details

  • Country / city: UK, Bristol
  • Year of construction: 2021
  • Installation time: 4 weeks
  • Application: Sewer rehabilitation
  • Installation: Trenchless technology
  • Technology: Hobas
  • Total length of pipe: 280m
  • Nominal diameter DN (mm): DN800
  • Nominal pressure PN (bar): PN1
  • Nominal stiffness SN (N/mm²): 32,000

Supply chain

  • Client: South Gloucester Council
  • Contractor: Matt Durbin Associates Ltd
  • Consulting engineer: South Gloucester Council
  • Structural GRP jacking pipe: Amiblu

Amiblu Structural Relining Pipes

Amiblu pipes have a smooth, resin rich internal surface with high abrasion resistance which consistently prevents fouling and build up, leading to low maintenance costs and high flow rates even at low gradients. Both Jacking and relining pipes are supplied with in-line flush joints which prevent the intrusion of roots and further ensure the integrity of the asset. Available in diameters from DN300 to DN3600, in varying strengths and lengths. Amiblu’s systems are cost effect, durable alternatives to traditional pipe systems.

 


For more information: Amiblu UK | +44 (0)7786 013574 | www.amiblu.com