Yeoford WwTW

Modular MBBR and lamella settlement technology delivered in 12 weeks to increase treatment capacity and support environmental compliance

Yeoford WwTW

Yeoford Wastewater Treatment Works required additional treatment capacity to accommodate increased flows while continuing to meet tighter environmental discharge consent requirements. To address these challenges, Purestream designed and supplied advanced wastewater treatment equipment as part of the upgrade works. 

The solution comprised two ST1300 Moving Bed Biofilm Reactor (MBBR) units and three lamella settlement tanks, specifically designed to treat the site’s flow requirements. By utilising modular equipment manufactured off-site, Purestream helped minimise on-site construction activities, reduce programme duration and lower delivery risk.

Yeoford WwTW

Delivered within a 12-week programme, the installation successfully increased treatment capacity while supporting compliance with revised environmental standards. The project demonstrates the benefits of modular wastewater treatment technologies in providing efficient, rapid-to-deploy solutions for utility clients facing growth and tightening regulatory requirements. 

Key features

  • Design and supply of advanced wastewater treatment equipment.
  • Two ST1300 MBBR units installed.
  • Three lamella settlement tanks provided.
  • Modular off-site manufactured solution.
  • Increased treatment capacity and supported environmental compliance.

Project Summary

  • Client: South West Water.
  • Project location: Yeoford, Devon.
  • Solution provider: Purestream Process Solutions.
  • Project duration: 12-weeks.

For More Information, contact us at https://www.purestreamdesign.com