Search
Nominate/Submit Case Studies
Job Board

Joseph Gallagher Ltd

Hinkley Point C – Fish Return

Delivery of a Complex Offshore Outfall Tunnel Through Precision Engineering

Aerial view of the Hinkley Point marine construction facility

Joseph Gallagher Ltd was appointed to deliver a technically demanding 1.8‑metre‑diameter, 620‑metre sea outfall tunnel using a pipe‑jacking methodology. The works required the controlled installation of a closed‑face TBM to be recovered above the seabed – an operation demanding high precision, detailed planning, and specialist offshore expertise.

Project Description

The company drove the tunnel from a restricted launch site along a complex alignment featuring double vertical curves and a challenging angled breakthrough. The TBM advanced through varying geological conditions before entering a 45‑metre offshore concrete structure, where breakthrough and recovery were carried out in a marine environment frequently affected by adverse weather and significant tidal variation. To maintain consistent progress, Joseph Gallagher adopted a closed‑face tunnelling method supported by a separation system designed to fully recycle process water, satisfying both the technical and environmental requirements of the project.

Challenges

The project introduced several major engineering challenges. The confined launch site required careful sequencing of all plant, equipment, and personnel. The TBM had to be launched and aligned at an angle, demanding highly accurate control throughout the drive. As face pressures increased, hyperbaric interventions of up to 2.4 bar were undertaken to ensure safe inspection and maintenance of the cutterhead. The double vertical curves required precise gyroscopic guidance, particularly as the TBM approached the offshore structure. Marine operations added further complexity, with variable weather and significant tidal fluctuations influencing offshore access windows.

JGL pipe‑jacking launch frame in position, ready for TBM installation during shaft preparation works

Expertise and Solutions

Joseph Gallagher Ltd applied its full tunnelling capability to meet these challenges. Specialist pipe‑jacking teams managed the drive using proven marine project methodologies, supported by experienced hyperbaric crews for pressurised interventions. Dedicated offshore lifting and tunnelling systems enabled safe recovery of the TBM above the seabed. Advanced gyroscopic navigation ensured alignment accuracy, while a fully integrated separation system allowed continuous recycling of process water.

NRC heavy‑lift crane operating alongside tunnelling plant in a busy urban construction site

Environmental performance was prioritised throughout. High‑quality pipe manufacturing ensured long‑term outfall durability. All process water was recycled, preventing marine discharge, and tunnel arisings were reused on site. Only biodegradable chemicals were used, and recovering the TBM in wet condition minimised seabed disturbance.

Value Added

Joseph Gallagher Ltd delivered the works on programme and within budget. Bespoke engineering solutions addressed the unique offshore breakthrough requirements, supported by the company’s strong hyperbaric experience.

Additional Capabilities

The project benefited from extensive resources across the Joseph Gallagher Group, including tunnelling systems supplied by SPA and lifting equipment from NRC, ensuring safe and efficient tunnelling and offshore operations.

Precast concrete tunnel segments stored and ready for installation

 


For More Information, contact us at https://www.josephgallagher.co.uk/

Tees Valley Pipeline
Deep shafts and tunnel construction providing critical water transfer infrastructure within the Tees Valley network.
Hinkley Point C - Fish Return
Delivery of a Complex Offshore Outfall Tunnel Through Precision Engineering
Tangmere Wastewater Treatment Scheme
Delivering Essential Wastewater Infrastructure for Southern Water at Tangmere WwTW