Donegan Civil Engineering
Detention Tank and CSO Screening – Witton Park, Blackburn
A 20m internal diameter, 4,500m³ detention tank with self-cleansing vac-flush system, resolving an unsatisfactory intermittent discharge to the River Blakewater
Detention Tank and CSO Screening - Witton Park, Blackburn
Client: United Utilities
Project Description / Main Operations
V J Donegan & Co Ltd completed this project direct for United Utilities as part of the larger Blackburn UIDs scheme. The purpose of the project was to resolve the unsatisfactory intermittent discharge (UID) from the combined sewer network to the River Blakewater.
The solution ensures that spill flows up to and including a 1 in 5 year return period are screened to a 6mm standard in two dimensions, and contributes to the River Quality Objective (RQO) for the River Blakewater.
Scope and method:
- Design and construction of a 20m internal diameter detention tank, stored volume 4,500m³, complete with vac-flush central column to be self cleansing.
- Reinforced concrete discharge chamber and reinforced concrete static screen chamber.
- 300mm diameter outfall sewer.
- Modifications to an existing CSO chamber in Preston Old Road.
- 110m of 700mm diameter auger-bore, with a 4.00m diameter drive shaft for its installation.
- 750mm diameter pipework from the detention tank to the River Blakewater via the new CSO chamber, and a reinforced concrete outfall structure.
MEICA scope
- Design and installation of 1 no. isolation penstock and 1 no. 750mm diameter flap valve.
- 2 no. submersible storm return pumps and 1 no. submersible scavenger pump.
- 1 no. tank flushing system, complete with vacuum pump, actuated valves, pressure and vacuum pipe, and flushing column diaphragm valve assembly.
For More Information, contact us at http://www.donegan.co.uk
Twin Storage Shafts - Langdale Way, Frodsham
Two shafts - 20.00m and 9.00m diameter - sunk within the playing field of a primary school
Shafts & Tunnelling
Stormwater Storage
Westminster Road, Macclesfield
Construction of an access chamber onto an existing brick culvert to provide an outfall for surface water
Ground Engineering
Sewers
Stormwater Storage
Weaverham WwTW
Green Asset Lab Enabling Works
Concrete Works
Chester Northgate Tunnelling – Chester City Centre
Client: Vinci PLC / Cheshire West & Chester City Council Value: £2,700,000 Project Description/Main Operations V J Donegan & Co Ltd were approached to work alongside Vinci PLC and Cheshire West & Chester City Council to provide a constructable solution for a new surface water outfall, from the Northgate Development Phase 1 in the heart […]
Ground Engineering
Sewers
Stormwater Storage
Tanks
The Airfields, Deeside
Large-diameter caisson and dewatering for regeneration infrastructure at the former RAF Sealand.
Ground Engineering
Precast Concrete
Stormwater Storage
Temporary Works & Shoring
Medlock CSO Screening
Client: Costain / United Utilities Value: £2,200,000 Project Description/Main Operations V J Donegan and Co Ltd was enlisted to collaborate with Costain in via their MSP Framework in partnership with United Utilities on the Medlock CSO Screening project. This initiative aimed to minimize the environmental impact of combined sewer overflows into the Medlock watercourse, an […]
Ground Engineering
Piling
Sewers
Stormwater Storage
Stormwater Storage
Tanks
Liverpool Waters, Stanley Dock – Civil Engineering Projects, Liverpool
Client: Excalon / Vital Energi Value: £600,000 Project Description/Main Operations V J Donegan & Co Ltd were approached by Excalon to provide a solution for laying 2 no. 710mm dia. gas pipes across Great Howard Street. Due to the high concentration of utility services within Great Howard Street it was deemed that an open-cut technique […]
Ground Engineering
Piling
Precast Concrete
Sewers
Tanks
Fujiclean Tank Installation – South Cheshire
Pioneering the FujiClean wastewater treatment system at Calverhall in collaboration with Costain and United Utilities.
Ground Engineering
Tanks
Temporary Works & Shoring