Storm Storage Shaft and Pipejacked Tunnel – St Dunstan’s Way, Bradford
A 20.00m diameter, 23m deep segmental shaft and 130m of pipejacked tunnel for Yorkshire Water
Storm Storage Shaft and Pipejacked Tunnel - St Dunstan's Way, Bradford
Client: Mott MacDonald Bentley / Yorkshire Water
Value: Approx. £1,900,000
Project Description / Main Operations
This project was carried out on behalf of Mott MacDonald Bentley, for Yorkshire Water. The contract included the construction of a 20.00m diameter segmental shaft approx. 23m deep, together with the associated tunnelling works.
Scope and method:
- Construction of a 20.00m diameter segmental shaft, 23.00m deep.
- Completion works to the above, including reinforced concrete base, benching, 1200mm diameter backdrop pipe, and 20.00m diameter precast concrete roof slab.
- Construction of an 1800mm diameter tunnel approx. 130m in length, by pipejacking techniques using a backacter tunnelling machine.
For More Information, contact us at http://www.donegan.co.uk
Twin Storage Shafts - Langdale Way, Frodsham
Two shafts - 20.00m and 9.00m diameter - sunk within the playing field of a primary school
Shafts & Tunnelling
Stormwater Storage
Westminster Road, Macclesfield
Construction of an access chamber onto an existing brick culvert to provide an outfall for surface water
Ground Engineering
Sewers
Stormwater Storage
Weaverham WwTW
Green Asset Lab Enabling Works
Concrete Works
Chester Northgate Tunnelling – Chester City Centre
Client: Vinci PLC / Cheshire West & Chester City Council Value: £2,700,000 Project Description/Main Operations V J Donegan & Co Ltd were approached to work alongside Vinci PLC and Cheshire West & Chester City Council to provide a constructable solution for a new surface water outfall, from the Northgate Development Phase 1 in the heart […]
Ground Engineering
Sewers
Stormwater Storage
Tanks
The Airfields, Deeside
Large-diameter caisson and dewatering for regeneration infrastructure at the former RAF Sealand.
Ground Engineering
Precast Concrete
Stormwater Storage
Temporary Works & Shoring
Medlock CSO Screening
Client: Costain / United Utilities Value: £2,200,000 Project Description/Main Operations V J Donegan and Co Ltd was enlisted to collaborate with Costain in via their MSP Framework in partnership with United Utilities on the Medlock CSO Screening project. This initiative aimed to minimize the environmental impact of combined sewer overflows into the Medlock watercourse, an […]
Ground Engineering
Piling
Sewers
Stormwater Storage
Stormwater Storage
Tanks
Liverpool Waters, Stanley Dock – Civil Engineering Projects, Liverpool
Client: Excalon / Vital Energi Value: £600,000 Project Description/Main Operations V J Donegan & Co Ltd were approached by Excalon to provide a solution for laying 2 no. 710mm dia. gas pipes across Great Howard Street. Due to the high concentration of utility services within Great Howard Street it was deemed that an open-cut technique […]
Ground Engineering
Piling
Precast Concrete
Sewers
Tanks
Fujiclean Tank Installation – South Cheshire
Pioneering the FujiClean wastewater treatment system at Calverhall in collaboration with Costain and United Utilities.
Ground Engineering
Tanks
Temporary Works & Shoring