Precast Concrete Culvert Installation – Brooks Lane, Middlewich

75m of precast concrete culvert and associated pipelines for United Utilities at Middlewich

Precast Concrete Culvert Installation - Brooks Lane, Middlewich

Client: United Utilities

Value: Approx. £300,000

Project Description / Main Operations

Excavation for and laying of precast concrete culvert, 2100mm x 1500mm and approx. 75.00m in length, together with associated pipelines and manholes.

Scope and method:

  • Excavation for and laying of 2100mm x 1500mm precast concrete culvert, approx. 75.00m in length.
  • 400mm diameter augerbore approx. 20m in length.
  • Various small diameter pipelines and manholes.