Supply Chain - Renewables & Energy Management - Hydro Electric
- Franklaw Power Recovery Turbine
Franklaw Power Recovery TurbineWhen United Utilities needed to increase the throughput of Franklaw Water Treatment Works in Lancashire they considered energy recovery as part of the overall design. Water is abstracted from the Thirlmere Aqueduct and conducted to the site through underground pipes. The water treatment process required that downstream of the energy recovery plant there should be a pressure of some 8m to drive the water through. Upstream however, there could be no possibility of pressure surge, due to the long pipeline. It was also imperative that water should flow at all times. Lightening strikes could potentially cause the set to trip and with some machine types this would result in either complete or partial shut down of the main. Gilkes were consulted and together with United Utilities engineers arrived at the solution seen in these images. An inlet chamber was always going to be required, this was built above ground and the mains conducted to it. [caption id="" align="alignnone" width="768"] Courtesy of Gilbert Gilkes & Gordon Ltd[/caption] A Gilkes Impulse Turbine could then be installed as the power recovery turbine as the plant now facilitated a free discharge machine. The turbine acts as both pressure and flow regulator for the intake works. In the event there is a loss of grid, the flow regulating needle valves, integral in the machines design, remain fixed until such time as mains power is recovered. Pressure continues to be broken by means of directing the needle jets at deflector plates inside the turbine case and the water falls to the intake chamber from where it continues in the normal way to the process plant. [caption id="" align="alignnone" width="768"] Courtesy of Gilbert Gilkes & Gordon Ltd[/caption]
Key statistics
- Head: 93 m
- Flow: 1.39 m3/s
- Power: 1000 kW
For more information: Gilbert Gilkes & Gordon | +44 (0)1539 720028 | www.gilkes.com
- Ross Priory Pumping Station
Ross Priory Pumping StationRoss Priory Pumping station is a Scottish Water asset situated in West Dunbartonshire. The purpose of the station is to transfer water from Loch Lomond to the WTW at Balmore. The Balmore WTW has the capacity to contribute 360 Ml/d of potable water for the city off Glasgow. The scheme is locally known as the Loch Lomond Water Supply scheme and is on a section of the Scottish Water network known as the cross connection between Strathblane and Balmore WTW.
Energy recovery
The Gilkes turbine provides two essential roles, primarily to reduce the pressure in the main and at the same time generate renewable energy for the benefit of Scottish Water. The Gilkes Turgo was selected as it is capable of continuously delivering pre-determined flows even in the event of a loss of grid situation. The Gilkes Turgo provides a proven and robust solution for pressure reduction and power generation in one box. Simply put the turbine is able to operate as a pressure reducing valve (PRV) whether it is functioning as a turbine or not. In a conventional reaction turbine, there is the risk that a grid trip would either require the turbine to shut down or for a complex by-pass arrangement to be in place. This Turgo turbine also avoids the possibility of pressure surge travelling back up the main. Due to the Turgo’s unique design, Gilkes engineers were able to achieve pressure reduction and power generation from a single machine without the use of hydraulics or additional valves. The Turbine is fitted with deflectors that allow water to continue passing through the turbine while at the same time being deflected away from the runner. This allows the machine to achieve a rapid shutdown, regardless of the spear valve (flow regulation) setting. This means that the flow through the turbine is not effected should the unit be required to shut down. The top and bottom deflector plates are mounted on vertical shafts supported by flanged bushes inside the turbine case. The deflectors are independent of each other and each unit is operated by its own electrical actuator mounted on the turbine case. Each deflector actuator has an integrated position transducer which indicates the deflector’s position for the full range of travel to the control system. The Turgo turbine is able to operate continuously as a pressure reducing valve (PRV). This is true whether the machine is operating as a PRV or as a PRV and turbine combined. [caption id="" align="alignnone" width="1200"] (left) 20" runner and (right) Turgo installation[/caption]Gilkes Turgo
Gilkes has considerable, worldwide experience of replacing the break pressure valve with a Turgo Impulse Turbine. The use of a Turgo Impulse turbine does not result in the plant using losing any flow control. The turbine may be set so that is primary purpose is to provide the correct value of water at the correct pressure. One of the great advantages of a Turgo Impulse turbine is that it generates within a wide variety of flows.Key statistics
Gilkes' scope of supply was for the supply, installation and commissioning of a Twin Jet Turgo hydro-turbine- Power: 735 kW
- Net Head: 80m
- Flow: 1000 l/s
- Runner Dia: 20”
- Speed: 750 rpm
For more information: Gilbert Gilkes & Gordon | +44 (0)1539 720028 | www.gilkes.com
- Stank Burn Hydro Scheme
Stank Burn Hydro Scheme
KEY STATISTICS
- Customer: Callander Community Hydro Ltd
- Net head: 146 m
- Flow: 348 litres/sec
- Turbine type: Gilkes Twin Jet Pelton
- Power (kW): 443 kW
- Dia: 650mm
- Speed: 750rpm
Scope of supply
- 650mm Twin Jet Pelton, fitted with hydraulic actuators.
- Synchronous Generator.
- Main inlet valve.Hydraulic control module.
- Turbine control and switchgear panel, complete with remote monitoring facility and head level sensors.
- Control and power cabling within turbine powerhouse.
- Installation & commissioning of Gilkes supplied equipment.
- Servicing of Gilkes equipment for 2 years.
For more information: Gilbert Gilkes & Gordon | +44 (0)1539 720028 | www.gilkes.com
- Pattack Hydro Scheme
Pattack Hydro Scheme
The Pattack hydro project is the largest storage project to be built in the Scottish highlands in recent years, and is the third scheme that Gilkes have been supplied equipment to on the Ardverikie estate. Previous schemes were in 1935 and 1986.
The project has a new mass concrete dam utilising 3,300m3 of concrete. It has created a new small lochan by impounding 196,000m3 of stored water, which is delivered to the turbine via a 6,500m penstock pipe.
Due to the storage element of this scheme Francis turbines were selected as the most suitable, achieving a peak efficiency of over 92%. The Gilkes designed control system employs sophisticated programming and algorithms, fine-tuned on site by Gilkes commissioning team, to maximise the storage potential of the site.
SCOPE OF SUPPLY: Full water to wire package including:
-
-
- 2 x Gilkes Francis Turbines
- 2 x 1000rpm Synchronous Generators
- 2 x Main inlet valves (Hydraulic weight to close butterfly valve)
- Control Panels
- Hydraulic Control Modules
- Installation
- Commissioning
-
The small footprint of the Francis turbines, and by close co-operation with the civils designers, enabled the powerhouse size to be minimised and also partially buried. This minimises any visual impact in this beautiful area.
The Ardverikie estate, on the shores of Loch Laggan, is a popular film location and has made appearances in several films and TV series.
Key statistics: Turbine 1 - Turbine type: Francis
- Mechanical power: 3068kW
- Electrical power: 2995kW
- Net head: 142
- Flow: 2390
- Runner diamater: 625
- Speed: 1000
Key statistics: Turbine 2 - Turbine type: Francis
- Mechanical power: 2053kW
- Electrical power: 1995kW
- Net head: 152
- Flow: 1525
- Runner diameter: 525
- Speed: 1000
For more information: Gilbert Gilkes & Gordon | +44 (0)1539 720028 | www.gilkes.com
-
- Avluburun Hepp Turbine Generator
Avluburun Hepp Turbine Generator
KEY STATISTICS
- Customer: ISU Genel Mudurlugu
- Turbine type: Streamline Pelton
- Number of turbines: 1
- Power: 170 kW
- Net head: 107.80m
- Flow: 0.18m3/s
- Runner dia: 550 mm
- Speed: 750 rpm
SCOPE OF SUPPLY
- Gilkes horizontal Streamline Pelton Turbine Model 550 P316 TJP
- Penstock connection pipe
- Turbine main inlet valve (MIV)
- MIV automatic pressure equalising bypass
- Synchronous generator 400V, 214.5 KVA, 0.9 PF
- Hydraulic pressure unit (HPU) for turbine, MIV and MIV bypass
- Turbine energy dissipating bypass valve
- Flowmeter
- Control and SCADA system
- Electrical balance of plant
- Delivery to the project site
For more information: Gilbert Gilkes & Gordon | +44 (0)1539 720028 | www.gilkes.com
- Bryn Cowlyd WTW
Bryn Cowlyd WTWBryn Cowlyd Water Treatment Works is in the county of Conwy in Wales and is fed from Llyn Cowlyd, which is the deepest lake in north Wales. The new WTW was commissioned in 2019 and is Welsh Waters flagship Works. Gilkes were approached by Skanska Construction for the detailed design, manufacture, testing and installation, commissioning and training of an energy recovery turbine suitable for flow control at the inlet to the works and to generate renewable energy which would contribute to the on site load required to operate the water treatment works. Welsh Water, Skanska and Gilkes worked together to determine the most suitable turbine and generator. With a net head close to 200m and a flow rate of around 323l/sec the hydrology was suited a Pelton turbine. After monitoring the expected variations, a 750mm single jet Pelton turbine was selected for efficiency and maximum annual energy production. [caption id="" align="alignnone" width="1200"] Bryn Cowlyd WTW single jet Pelton installation[/caption] It was an interesting project for Gilkes, as this was the first water treatment works where the entire project was done under BIM (Building Information Management) meaning a full 3D walk though of the treatment stages, energy recovery turbine and final treatment was available during the design stage and also for hazard awareness. Although the turbine could have been offered in a compact, Streamline format, the machine was offered in a more heavily built design to ensure that noise from the turbine was kept to a minimum. Gilkes are proud to have supplied further equipment for use on Welsh Water sites, having delivered three machines over the last 10 years. [caption id="" align="alignnone" width="1200"] Bryn Cowlyd WTW single jet Pelton installation[/caption] KEY STATISTICS
- Turbine Type: Single Jet Pelton
- Power: 575kW
- Head: 217 m
- Flow: 323 l/s
- Runner Dia: 750 mm
- Speed: 750 rpm
- Reducing spool & inlet pipework
- Single Jet Pelton turbine
- Induction generator
- Turbine control & switchgear panels
- Operation & maintenance manuals
- Installation & commissioning
- Operator training
- Ongoing service & maintenance
For more information: Gilbert Gilkes & Gordon | +44 (0)1539 720028 | www.gilkes.com
- Keltie Water Hydro Scheme
Keltie Water Hydro Scheme
KEY STATISTICS
- Customer: Drummond Estate
- Turbine type: HCTI Twin Jet Turgo
- Number of turbines: 1
- Power output: 1MW
- Net head: 78m
- Flow: 1626 l/s
- Runner diameter: 25”
- Speed: 600 rpm
Scope of supply
- 25” Twin Jet Impulse Turbine
- Main Inlet Valve
- Synchronous Generator
- Lube Oil System
- Control & Switchgear Panel
- Hydraulic Control Module
- Head Level Sensor
- Control & Power Cabling
- Building Services
- Transformer
- Installation & Commissioning
- Servicing for duration of warranty
For more information: Gilbert Gilkes & Gordon | +44 (0)1539 720028 | www.gilkes.com
- Glencorse WTW
Glencorse WTWScottish Water’s £130m flagship investment set just outside the Edinburgh ring road is a 21st century replacement for two now decommissioned WTWs at Alnwickhill and Fairmilehead. Glencourse is fed by the Talla Aqueduct and the water comes from a variety of sources, primarily the Talla, Megget and Fruid Reservoirs. Employing DAF pre-treatment, tertiary sand filtration and final disinfection, the works is able to provide up to 175Ml/d of potable water to the Scottish capital. As with any physical or biological treatment system maintaining a steady flow though the works is paramount to its stable and efficient operation. Due to the varying head and flow characteristics, Black and Veatch (Scottish Waters delivery partner) approached Gilkes for a solution to pressure management at the inlet to the works. Two possibilities were considered including pressure reducing valves (PRV’s) and also a hydro turbine to manage the pressure and provide a steady flow to the DAF cells. [caption id="" align="alignnone" width="1200"] Glencorse WTW twin jet Turgo installation[/caption] The Gilkes Turgo was selected as it is capable of continuously delivering pre-determined flows even in the event of a loss of grid situation. The Gilkes Turgo provides a proven and robust solution for pressure reduction and power generation in one box. Simply put the turbine is able to operate as a pressure reducing valve (PRV) whether it is functioning as a turbine or not. In a conventional reaction turbine, there is the risk that a grid trip would either require the turbine to shut down or for a complex by-pass arrangement to be in place. This Turgo turbine also avoids the possibility of pressure surge travelling back up the main. The energy recovery turbine at Glencorse captures 30-35% of the energy needed to run the WTW. This helping to reduce the sites carbon footprint and dependence on external energy sources. Due to the Turgo’s unique design, Gilkes engineers were able to achieve pressure reduction and power generation from a single machine without the use of hydraulics or additional valves. The Turbine is fitted with deflectors that allow water to continue passing through the turbine while at the same time being deflected away from the runner. This allows the machine to achieve a rapid shutdown, regardless of the spear valve (flow regulation) setting. This means that the flow through the turbine is not effected should the unit be required to shut down. The top and bottom deflector plates are mounted on vertical shafts supported by flanged bushes inside the turbine case. The deflectors are independent of each other and each unit is operated by its own electrical actuator mounted on the turbine case. Each deflector actuator has an integrated position transducer which indicates the deflector’s position for the full range of travel to the control system. [caption id="" align="alignnone" width="1200"] Glencorse WTW twin jet Turgo installation[/caption] The Turgo turbine is able to operate continuously as a pressure reducing valve (PRV). This is true whether the machine is operating as a PRV or as a PRV and turbine combined. Gilkes has considerable, worldwide experience of replacing the break pressure valve with a Turgo Impulse Turbine. The use of a Turgo Impulse turbine does not result in the plant using losing any flow control. The turbine may be set so that is primary purpose is to provide the correct value of water at the correct pressure. One of the great advantages of a Turgo Impulse turbine is that it generates within a wide variety of flows. [caption id="" align="alignnone" width="1200"] Glencorse WTW twin jet Turgo installation[/caption]
KEY STATISTICS
- Turbine Type: Twin Jet Turgo
- Power: 253 kW
- Net head: 53 m
- Flow: 550 l/s
- Runner diameter: 20”
- Speed: 600 rpm
SCOPE OF SUPPLY
- Turbine and control system
- Installation
- Commissioning
For more information: Gilbert Gilkes & Gordon | +44 (0)1539 720028 | www.gilkes.com
- Derby Hydro Power House
Derby Hydro Power House
Scope of works
The purpose of the job was to design and supply temporary and permanent support for a hydro power house and turbine chamber (plus associated inlet channel and tailrace) constructed at the side of an existing weir on the banks of the River Derwent in the centre of Derby.Issues & solutions
The design incorporated a single level of modular 406UC Hydraulic Brace system in conjunction with Larssen piles up to 10m in length, toed in mudstone, covering a perimeter of over 150m. MGF's design allowed early removal of the brace by using a permanent concrete base slab as a low propped cantilever. The design had to take into consideration the complicated construction sequence; and the location of a large crane during installation and removal of the river piles. During the project Balfour Beatty and MGF collaborated to develop the Stairsafe system (the UK's first temporary steel stair system designed specifically for excavations). The system proved a great success in providing rapid and safe access into excavations leading to greater site productivity. The system is now being used throughout the UK on excavations up to 6.5m in depth. [caption id="" align="alignnone" width="1200"] Courtesy of MGF Ltd[/caption]Project details
- Sector: Energy & Waste
- Client: Derby County Council
- Contractor: Balfour Beatty
- Consulting engineer: Atkins
- MGF Depot: Midlands - Rugeley
- Product hired: 406UC Hydraulic Brace, 10M Larssen Piles
The verdict
From early in the tender process MGF have been heavily involved with Balfour Beatty to develop an innovative, cost effective and highly complicated cofferdam design; which helped make Balfour Beatty's tender attractive to the client, Derby City Council. Michael Rummens, Balfour Beatty Site Agent, commented:"MGF were brought in at tender stage to assist in the value engineering of the cofferdam and support frames. Upon contract award, MGF's technical team were extremely proactive in producing a workable design in line with the projects requirements. The professional, amenable and expedient attitude continued throughout the process from design, technical support, plant hire and delivery and site assistance."
For more information: MGF Ltd | +44 (0)1942 402700 | www.mgf.co.uk