Supply Chain - Water Pumping Stations
- Sandown Surface Water Abstraction
Sandown Surface Water AbstractionSandown Surface Water Abstraction (SWA) is a pumping station abstraction from the River Yar on the Isle of White, which feeds raw water into the Sandown WTW. The pumping station is several hundred metres from the water treatment works, and sits alongside the popular and busy Red Squirrel Trail walking route and cycle path. Along with many other water intakes throughout the UK, Southern Water had to upgrade the water intake screens to be compliant with the Eel Regulations, which meant a bar-spacing that did not exceed 2mm and an approach velocity that did not exceed 0.25 m/s. The existing intake structure was built in the early 1980s and consisted of interlocking steel sheet pile walls, capped with a concrete slab. Manholes on top of the slab provided access to the sump pumps, valves and pipe/cable ducts. The river bed in front of the structure is a flat concrete slab, which could provide a good base for the eel screens to sit on if needed. [caption id="" align="alignnone" width="1200"] (left) Concrete slab on top of the sheet-pile pump and valve enclosure and (right) sheet-pile walls that make up the pump enclosure[/caption] [caption id="" align="alignnone" width="1200"] (left) View inside the pump chamber, looking at the sheet piling adjacent to the river. Below the waterline is the 0.2m high x 3m wide slot where the river water is drawn through. (right) close-up of intake drawing showing ‘letterbox’ slot[/caption] The existing intake did not have any screening; hence fish, eels and other objects could potentially enter the pump chamber. CMDP was the main contractor for the project, and GoFlo worked closely with them from the early design stages to the final commissioning to ensure an optimal solution was developed. With a maximum abstraction flow rate of 0.278 m3/ second, the approach velocity through the existing intake slot in the sheet pile wall would exceed the maximum specified in the Eel Regulations. This meant that would it would not be possible to install the GoFlo screens inside the existing pump building and would have to be installed externally to the existing building. An added complication was that the intake could not be shut down for more than 8 hours without severely disrupting the water supply to the Isle of White, which would not be acceptable, so the solution had to be designed to be installed into a working intake using divers. GoFlo had a similar issue at another Southern Water site (Springfield), and for that site designed a fabricated ‘intake box’ system that could be installed by divers. This system worked well, so the principle was used for Sandown, even though the water depth at Springfield was 4.5m, whereas at Sandown it is typically only 600mm. The width of the screens at 3.55m has been determined by the minimum depth of water in the river (0.438m) while still having to meet the 0.25 m/s approach velocity under the Eel Regulations while abstracting the maximum flow rate.
Site survey
The design process started with a detailed survey of the intake area. As is the case with many sheet-pile structures, nothing was exactly plumb or square, so because the fabricated intake box we would have to manufacture had to fit perfectly, first time, we had to enter the river and make plywood templates that fitted the profile of the existing structure perfectly. At the same time a detailed level-survey was conducted on the river bed concrete slab. We took the wooden templates away and turned them into precise profile data points that could be used to build an accurate 3D model of the existing structure in our CAD system. Based on that, we could design the intake box to fit perfectly.Design
Due to how the in-pans and out-pans of the sheet piling were positioned, the bolted connections onto the Intake Box at the upstream end was on an out-pan and at the downstream end on an in-pan, so the left and right-hand intake box sides being different widths (1560mm and 1450mm). [caption id="" align="alignnone" width="1200"] (left) Intake box side drawing and (right) plan drawing showing new intake box attached to existing sheet-pile structure[/caption] The intake box is a stainless steel fabricated box made up of the two sides and a baseplate that were assembled into a finished box on-site. The structure is designed to be a rigid structure so it could support the screens in the inclined ‘operating’ and vertical ‘service’ positions. The Intake Box structure also had the walkways fixed to it, which in turn have the security fencing fixed to them, so had to be designed to be very strong. A course bar screen with 50 mm bar-spacing was incorporated into the intake box, just upstream of the screens. This bar screen will protect the fine GoFlo screen meshes from large debris which could deform or puncture the screen face during flood flow conditions, but also keep any swimmers away from the moving parts! An advantage of having the screens perpendicular to the river flow will reduce the possibility of the bar screen collecting debris; the river passing flow tending to pull material away from the bars. [caption id="" align="alignnone" width="1200"] (left) Drawing of intake box with course bar screen attached to upstream face and (right) drawing showing GoFlo screens, debris trough and intake box attached to existing structure[/caption] The debris captured by the screens is returned to the river via the debris trough and return channel, but about 5m downstream, so the likelihood of material being pulled back into the screens is minimised. The walkway structure incorporates davit sockets and removable winches. The winches are used for pulling the screens from their inclined ‘operating’ position to the vertical ‘service’ position. From here, the screen’s motor/gearbox and drive system can be accessed safely. Should a motor need to be taken off the screen, a portable davit can be mounted in a dedicated floor socket and the motor lifted up and over the handrail onto a trolley for transport away from the area. [caption id="" align="alignnone" width="1200"] Complete 3D model of proposed GoFlo system attached to the historic structure[/caption]Installation
This started with the river bank and floor being cleared of any silt and stones etc. Next, the intake box was assembled, including adding some temporary diagonal braces to keep the sides an baseplate square and to prevent the structure flexing during lifting. Once the intake box was in the river and fixed in position the diagonal braces were removed. The intake box was fixed down to the concrete apron using stainless steel M16 resin-fixed anchors, and to the vertical sheet pile wall by drilling a tapping M12 bolted fixings. Installing such a structure in a flowing river was a hazardous operation, especially with divers in the water to guide it into position, drill and install the fixings into the wall and river bed. Underwater visibility was very poor due to unseasonal heavy rainfall and increased river flow. The divers had to be in constant radio contact with the dive support team on the bank. The divers also had a live video feed to the team in the control room so they could be guided to the fixing locations. [caption id="" align="alignnone" width="1200"] (left) Lifting the intake box into the river and (right) lifting the first of the GoFlo screens into the intake box[/caption] Once the intake box was fixed in place the two GoFlo screens were lifted into position. This is a relatively quick operation due to the integrated ‘pivoting frame’, which are guide rails allowing the screen to be lifted in vertically and accurately guide the screen into position, even when the intake is flooded with zero visibility. At this point the screens were connected to a temporary control panel and a wooden debris trough was constructed to allow the screens to be put into operation. The screens had to be put into service immediately because of the looming deadline to make the Intake Eel Regulations compliant. [caption id="" align="alignnone" width="1200"] (left) The first screen in position on the intake box and (right) both GoFlo screens in position in the intake box[/caption] A few months later the walkways, debris trough and security fencing were fitted, which all bolted directly to the intake box. The assembly was all designed in detail using 3D CAD software by GoFlo, then the constituent parts laser-profiled and CNC folded, finally being welded together. The walkways were installed in two days, and the debris trough in a similar time, which is testament to the accuracy of the design and fabrication undertaken by GoFlo. [caption id="" align="alignnone" width="1200"] Completed GoFlo screen installation[/caption]For more information: GoFlo Screens Ltd | +44 (0)1453 884400 | www.gofloscreens.co.uk
- Sandown WSW
Sandown WSW
Southern Water’s Sandown Water Supply Works is located on the south-east of the Isle of Wight and supplies drinking water to Sandown and Shanklin. The average winter demand of 7.7 Ml/d can almost double up to 13 Ml/d in the summer due to tourism. Southern Water’s Asset Strategy requires a reliable supply of 12 Ml/d of treated water from the works. A risk assessment to establish resilience of the works' infrastructure identified the ageing clear water tank and high lift pumping station as potential weaknesses which could affect supply. Southern Water awarded Trant Engineering a £10m design and construct contract, Phase 1 for the replacement of these assets. Phase 2 of the project works is for improvement of wash water discharge and flood resilience on site, and Phase 3 includes installation of new caustic soda offloading and storage facilities together with new dosing equipment installed in a new GRP kiosk.
The story so far
The new Phase 1 high lift pumping station will deliver up to 8 Ml/d to Shanklin Service Reservoir and up to 14 Ml/d to Brading Service Reservoir via existing ultraviolet reactors along with the power supply and motor control centre (MCC2). The contract also covers extensive pipework modifications and the installation of new supply flow meters, treated water aluminium monitoring and triple validated contact tank outlet chlorine residual monitoring. Prior to commencing on site, Trant undertook a series of surveys and investigations which identified a number of construction challenges. In addition to the requirement to keep the works in operation during the work, the site is located within an AONB, which required planning permission and environmental mitigations being satisfied for limited environmental impacts. Due to site space constraints and the need to cut down disruption to live treatment plant, Trant identified early on that the need to build the new equipment offline as far as possible and to provide a new incoming power supply, so that the new equipment could be powered up and tested independently of the existing works. [caption id="attachment_16889" align="alignnone" width="1200"] The new glass-coated steel sectional clear water tanks - Courtesy of Trant Engineering[/caption]Innovative design
To reduce excavation work, Trant proposed a design using two new glass-coated steel sectional clear water tanks, 6m diameter and 7m high, constructed above ground on a brownfield area of the site. The tanks feed two sets of five, vertical multistage pumps, one set for Brading and one for Shanklin, installed above ground mounted on concrete plinths, with a surrounding steel access platform with staircase at either end. Due to the level of the outlet of the contact tank being below ground, an intermediate 're-lift' pump station was introduced to feed the clear water tanks. The re-lift pumping station used a jacketed shaft construction method to avoid heavy temporary works. Southern Water’s Senior Project Manager, Kev Fausset said:“Trant was very pro-active in proposing innovative designs to minimise below-ground works and build off line for least disruption to live process works. That has helped to maintain supply and reduce the overall programme of works.”
[caption id="attachment_16888" align="alignnone" width="1200"] Inside one of the new glass-coated steel sectional clear water tanks - Courtesy of Trant Engineering[/caption]Looking forward
Trant started on site in September 2023 and the scheme has made a great start with significant progress on the civil construction works. However, a high volume of complex works remains to be delivered on the scheme within what is a challenging programme and site environment. Tony Jacobson, Trant’s Senior Project Manager said:“Success will be achieved through ongoing collaboration with our client, supply chain and the wider water industry. The new clearwater tanks will be installed during the summer and the new MCC and electrical work will be completed in time for the arrival of the new pumps in the last quarter of 2024. Simultaneously, we are progressing the mechanical and electrical works for Phases 2 and 3 so that the project delivers on all its objectives and provides an excellent standard of new and upgraded assets.”
For more information: Trant Engineering Ltd | +4423 8066 5544 | www.trant.co.uk |
- Albert Street Eel Screens
- Springfield Surface Water Abstraction
Springfield Surface Water Abstractio...Springfield Surface Water Abstraction (SWA) is a Southern Water pumping station located on the banks of the River Medway in Maidstone, Kent and transfers water to Eccles Lake. The intake is positioned flush with the riverbank and consists of two openings into an underground concrete intake structure, with a busy riverside towpath on top. The picture above is before any works started. There are two coarse bar screens, one in front of each opening and a fixed timber boom in the river in front of the intake to deflect large debris. The flow travels approximately 25m by gravity into the pump house building, then is pumped to Eccles Lake and from there under gravity to Burham Water Supply Works. To comply with The Eel Regulations, Southern Water had to upgrade the intake so that the maximum bar-spacing on the intake was 2 mm and the velocity of the water approaching the screen did not exceed 0.25 m/s. This is to prevent juvenile ‘glass eels’ from being sucked into the intake which would prevent them from moving upstream into the Medway catchment and beginning the long and complex life cycle of the European eel. The 0.25 m/s approach velocity could be achieved by using only half of the existing intake, with the other half blocked up using a concrete stop-log. GoFlo Screens were awarded the contract to supply and assist with the installation of the eel screens at this location, by Trant/BTU Utilities Ltd. The site is particularly complicated because it is in use 24/7, and cannot be turned off for more than a day or two before disruption to Burham Water Supply Works would occur. Coupled with this, the site cannot be de-watered, so would have to be installed by divers in water that is 4.5 metres deep, with very low underwater visibility. The new GoFlo screens are too large to fit inside the existing concrete structure, so had to be accommodated outside of the existing concrete structure, in a prefabricated stainless steel ‘intake box’ that sits on the existing underwater concrete apron. GoFlo designed and manufactured the GoFlo screens, intake box, walkways and debris trough. Everything had to be designed to be simple and modular so that the underwater elements could be installed by divers. The elements supplied by GoFlo are shown below along with the basic specification:
- Screen drive: 2.2 kW 3-phase WIMES-spec motor/gearbox
- Maximum bar spacing: 2mm
- (Single) screen mesh area: 4.652m2
- Angle of inclination (from horizontal): 72.5°
- Construction material: 304 stainless steel
Proposed design
The overall design of the system was developed collaboratively between the main contractor (Trant/BTU), the client (Southern Water), Atkins Global who were the M&E designers working for Trant/BTU and GoFlo Screens. GoFlo also worked closely with Commercial and Specialised Diving Ltd to incorporate their ‘diver design friendly’ feedback into the design to make it easier for the divers to install, which was especially important considering it would be installed in the middle of winter. Before the detailed design could begin, the intake and apron area in front had to be cleared of silt and debris. Once in the water the divers found a tangled mess of silt, fishing line, a large quantity of steel railing, two motorbikes, a pushbike and various other debris! Once the debris was cleared, a detailed site survey was undertaken to determine how flat the apron was, the exact profile of the vertical concrete piers which the GoFlo intake box would fix onto (a special 5-metre-long profile gauge was manufactured to achieve this), and check how far the apron extended out into the river. A number of differences were found between the original construction drawings from the 1960s and what was actually built. Following the site survey, a detailed 3D model of the intake was constructed in Inventor software which formed the basis of the GoFlo design. The principle of the GoFlo design was a modular construction, comprising of:- A fixing frame that fixed to the concrete structure and was used as a template for drilling the fixing holes.
- A sacrificial ‘measuring frame’ which bolted to the fixing frame to allow all of the key levels to be measured (hence adjusted) from above-water.
- 2 x intake box sides which bolted to the fixing frame (assembled above-water, after the fixing frame fixing holes had been drilled and the fixing frame removed).
- The standard GoFlo baseplate and pivoting frame (guide rails), 2 off.
- The standard GoFlo screen(s).
- Coarse debris screen/walkway that integrated with the Intake box/debris trough and return channel.
- Two reference brackets installed on the above-water concrete upstand, which provided two precise reference points for the fixing frame to locate onto at top end.
- The fixing frame, which once positioned acted as a drilling template for all of the fixings into the concrete structure. At each fixing position there is an 18.5 mm diameter hole, to allow an 18 mm masonry drill bit to pass through which was used as a guide for drilling. These 18 mm diameter holes, once the fixing frame was removed, had Hilti HKD-SR stainless-steel M16 fixings installed.
- For precise positional adjustment, the fixing frame had 2 x M16 height adjusting bolts close to the toe of the intake apron, 2 x M16 stand-off adjusting bolts at the bottom of the vertical and two temporarily-fixed adjustment blocks at the bottom of the vertical frame members to allow the frame to be pushed/pulled both laterally and longitudinally, and once in position locked in that position for the fixings to be drilled. These were removed once the intake box was finally installed.
- The fixing frame was designed to stand-off the concrete by a nominal distance of 20 mm to allow for unevenness in the concrete structure. This gap was taken-up at each fixing point using a stainless-steel shim stack. The height of the required shim stack was measured after the fixings holes had been drilled, but before the fixing frame was removed so that the shim stacks for each fixing point could be pre-prepared. Fine adjustment was still possible by adding/removing shims later as required.
- Once the fixing holes had been drilled, the fixing frame was removed, then the intake box sides bolted on, the GoFlo baseplates and pivoting frames attached. This allowed the whole intake box to be lifted in as an assembled unit and fixed in place using the pre-prepared fixings and shim stacks. Apart for the minor adjustments to levels, this saved a lot of complex underwater assembly work.
- Once the intake box was fixed in position, the coarse debris screen and walkway were fixed onto the intake box, then the GoFlo screens were installed.
Construction
The photos below show the actual parts being installed on site. Bear in mind that the water is 4.5 metres deep, and the GoFlo screen 6.1 metres long. The first photo shows the fixing frame lying on its back, having the measuring frame bolted to it prior to being lifted in. The second photo shows the assembled fixing frame and measuring frame being lifted into position. You can see that the river was very high after several days of heavy rain. [caption id="" align="alignnone" width="1200"] (left) Fixing frame and measuring frame being assembled and (right) fixing frame and measuring frame being lifted into the intake – note the very high water levels![/caption] The fixing frame and measuring frame in position, ready for the fixing holes to be drilled. The mild steel measuring frame was sacrificial, but provided above-water horizontal references for a spirt level, which was essential during levelling. Once the drilling was completed, the fixing frame and measuring frame were removed from the water, then the intake box sides, GoFlo screen baseplates and pivoting frames assembled together. [caption id="" align="alignnone" width="1200"] (left) Fixing frame and measuring frame in position and (right) the intake box being assembled prior to final installation[/caption] [caption id="" align="alignnone" width="1200"] (left) The fully assembled intake box, (middle) lifting the assembled intake box into the intake with a 60-tonne crane, and (right) the assembled intake box was attached to the concrete structure by divers which took several days[/caption] Next, the coarse bar screen was lifted into position, closely followed by the GoFlo Screens. GoFlo screens are lifted in vertically and use the pivoting frames as guide rails to guide the screen precisely onto the baseplate. [caption id="" align="alignnone" width="1200"] (top left) Lifting the course bar screen into the intake box, (bottom left) lifting the first GoFlo screen into the intake box, and (right) fitting the front part of the walkway structure onto the intake box[/caption] The screens are designed to discharge the collected debris into a dedicated trough behind the screens. The trough is made from stainless steel (as are the screens, intake box and coarse bar screen). The trough has a high back to catch the spray (2.5 bar water pressure) that is emitted from the screen spray-bars behind the mesh belt. Each screen has a spray bar with multiple nozzles fed by a remote water booster pump located inside the main building. Debris on the surface of the screen mesh as it rotates falls off as it runs over the top sprockets, while any remaining ‘sticky’ debris is blasted off by water the jets from the inside of the screen and into the trough. [caption id="" align="alignnone" width="1200"] (top left) Fitting the debris trough and return channel, (bottom left) the spray boom assembly which fits inside the screen mesh, and (right) completed walkway structure attached to the intake box[/caption] The debris trough includes a dedicated water feed (10 litres/second) to flush collected material back into the river downstream of the screens. The green fence posts are to support the security fence to protect the public from the machinery. [caption id="" align="alignnone" width="1200"] (left) The debris flushing flow pipework underneath the debris trough and (right) the security fencing being fitted[/caption] 10 cm bar-spaced coarse debris screen protects the GoFlo screens from large object damage, and keeps swimmers out. Due to the proximity of the screens to the footpath and the possibility of ice formation in winter months, a fully enclosed debris trough was required to confine the spray mist. The covers are hinged to enable full unrestricted access to the trough. [caption id="" align="alignnone" width="1200"] (top left) View from the-screens, looking out towards the river, (top right) the lids covering the debris trough, (bottom left) further lids covering the debris return channel and (bottom right) the completed installation, inside the security fencing[/caption] [caption id="" align="alignnone" width="1200"] The completed installation, looking upstream[/caption]For more information: GoFlo Screens Ltd | +44 (0)1453 884400 | www.gofloscreens.co.uk
- Civil Engineer - Water (6331)
Civil Engineer - Water (6331)
The opportunity
Do you have a passion for Civil Engineering ? Are you driven to create solutions for the unprecedented climate, environmental, and efficiency challenges facing our clients and the wider community? Then make a real difference and join us at Stantec! We are excited to continue our growth journey in Ireland and Northern Ireland and we have exciting plans for expansion in 2025 and beyond. We look forward to continuing our work with Uisce Eireann on the Engineering Design Services Framework and in Northern Ireland, we are proud to have been appointed to Northern Ireland Water’s IF182 Professional Services Framework. Taoiseach Simon Harris recently opened our new Dublin office, and we have now also moved to a new city center office in Belfast. This exciting pipeline of work, coupled with the scale of opportunity across the AMP8 cycle in the UK means that we seeking Civil Engineers at all levels with experience in the water/wastewater industry to join us. We are flexible with location so the position can be based in Dublin, Belfast or elsewhere. You will have the opportunity to join a dynamic team spread across the UK and Ireland, supporting the delivery of a variety of projects as part of a major capital investment programme.You will play an important role in the team, developing technical solutions & providing advice to our clients. You will provide technical expertise to ensure projects are delivered to cost, schedule & quality standards and work collaboratively amongst multi-disciplinary teams to ensure first class delivery of our projects. You will work closely with external stakeholders & clients to develop long term relationships.About You
You will be Degree qualified (or equivalent) in Civil Engineering or other relevant subject and have some experience of working within the regulated water industry.You will have knowledge of water and wastewater infrastructure/networks and treatment. Due to the nature of upcoming projects, ideally, you will also have experience in areas such as Clean Water and Wastewater Treatment, Trunk Mains and Large Diameter Pipeline Design.Ideally, you’ll have previous consultancy experience in a design role.Most importantly, you’ll embody our values and ethos of client focus and service excellence and have a passion for making a difference in the Water sector.Why Join us?
- Our People Culture: We're a close knit team and very proud of our friendly and collaborative environment
- Growth: We're on an exciting growth journey in Ireland and Northern Ireland - we want you to be part of it!
- Awards: Stantec were awarded the International Consulting Firm of the Year and Best place to work - Large Consulting Firms at the 2024 NCE awards as well as being consistently recognised in the top 10 Corporate Knights most sustainable companies in the world.
- Great Benefits: Competitive salary, pension plan, holidays, free private medical insurance, discounted gym membership and lots more.
- Flexible working arrangements
- Great Projects: We have secured positions on both the Uisce Eireann and NI Water Frameworks and are delivering a wide variety of projects that will make a real difference to our communities
- Industry leading training and development as well as paid for professional subscriptions
About Stantec
The Stantec community unites more than 31,000 employees working in over 450 locations across 6 continents. We have been working with our clients and communities in the UK for over 150 years. We plan, design, deliver and manage the development and infrastructure needed to support the creation of sustainable, healthy and prosperous communities. Our teams provide effective and relevant solutions, translating our clients’ vision into valued consents, deliverable plans for projects and programmes, and efficient designs for delivery, based on technical excellence and deep market insights. We deal with today’s challenges, but also keep a fairer, better tomorrow in sight, looking at how we deliver clean growth, support radical changes in our economy and meet the needs of future communities. Stantec provides equal employment opportunities to all qualified employees and applicants for future and current employment and prohibit discrimination on the grounds of race, colour, religion, sex, national origin, age, marital status, genetic information, disability, sexual orientation, gender identity or gender expression. We prohibit discrimination in decisions concerning recruitment, hiring, referral, promotion, compensation, fringe benefits, job training, terminations or any other condition of employment. Stantec is in compliance with laws and regulations and ensures equitable opportunities in all aspects of employment. Building an inspired, inclusive work environment that attracts, supports, and develops world-class talent is a crucial key to our success. If you are excited by this role but worry that your experience doesn’t exactly align, we encourage you to apply. - Senior Civil Engineer - Water (6286)
Senior Civil Engineer - Water (6286)
The opportunity
Across the entire business, Stantec are building on top of what’s already been a highly successful period of growth. Our strategy within the Water division for 2023 and beyond is creating a number of new exciting opportunities across the business. We partner with the top water clients across the UK, work on some of the largest, most iconic water projects in the industry and we promise to design with community in mind by reducing environmental impacts and improving social impacts. We enable the delivery of sustainable development and infrastructure projects that adapt to and mitigate the effects of climate change. Our Civil Engineers work across the project lifecycle in asset planning / strategy, concept design, outline design and detailed design. We work in a variety of project areas within the water sector, including clean water treatment and networks, wastewater treatment, wastewater networks, flooding, and urban drainage. You can find out more about our work in the water sector here: Stantec H2O+U - UK. You’ll be responsible for the project’s civil engineering design, the leadership of civil engineering teams and will work alongside our overall project design leads to ensure successful project delivery and outcomes for our clients. You will also have access to Stantec’s world-class expertise to help you deliver cutting edge design.About You
You’ll have experience working as a Civil Engineer on projects within sectors such as the water, environment or other related infrastructure sectors. Ideally you will hold Chartered or Incorporated member status with a relevant professional body such as ICE or CIWEM. You’ll have a passion for the water and environment sector and supporting our developing civil engineers. You’ll also be experienced in successful project delivery and working collaboratively with project teams to develop innovative solutions. Finally, you will have experience of working in a client facing role, leading client engagement and collaboration on a regular basis.
About Stantec
The Stantec community unites more than 31,000 employees working in over 450 locations across 6 continents. We have been working with our clients and communities in the UK for over 150 years. We plan, design, deliver and manage the development and infrastructure needed to support the creation of sustainable, healthy and prosperous communities. Our teams provide effective and relevant solutions, translating our clients’ vision into valued consents, deliverable plans for projects and programmes, and efficient designs for delivery, based on technical excellence and deep market insights. We deal with today’s challenges, but also keep a fairer, better tomorrow in sight, looking at how we deliver clean growth, support radical changes in our economy and meet the needs of future communities. Stantec provides equal employment opportunities to all qualified employees and applicants for future and current employment and prohibit discrimination on the grounds of race, colour, religion, sex, national origin, age, marital status, genetic information, disability, sexual orientation, gender identity or gender expression. We prohibit discrimination in decisions concerning recruitment, hiring, referral, promotion, compensation, fringe benefits, job training, terminations or any other condition of employment. Stantec is in compliance with laws and regulations and ensures equitable opportunities in all aspects of employment. Building an inspired, inclusive work environment that attracts, supports, and develops world-class talent is a crucial key to our success. If you are excited by this role but worry that your experience doesn’t exactly align, we encourage you to apply. - Senior Civil Engineer (6463)
Senior Civil Engineer (6463)
The Opportunity
Following a number of successful frameworks bids across the water industry, and in preparation for the most challenging AMP ever, we are expanding our high-performing engineering teams across the country. In Newcastle, we are excited to have been appointed as a Strategic Technical Partner by Northumbrian Water for the AMP8 period. Stantec provide a range of technical enabling, solution delivery and design services to support Northumbrian Water in achieving its vision to be the leading provider of sustainable water and wastewater services. As part of our long-standing relationship with Northumbrian Water, including the ongoing ESH-Stantec joint venture, we will continue to develop innovative solutions to support their delivery of capital investment across both infrastructure & non-infrastructure projects. In order to continue providing our clients with our expert service, we are looking to recruit a Senior Civil Engineer into our team Newcastle on the picturesque Quayside. You will become part of an international team, redefining our landscape with sustainability, the environment and the communities we serve at the heart of everything we do. As a Senior Civil Engineer, you will work across the entire project lifecycle in asset planning, strategy, concept design, outline design & detailed design. You’ll be responsible for delivering civil engineering solutions, guided by our Principal Engineers & Design Leads, whilst also supporting & mentoring our more junior engineers.You can find out more about our work in the water sector here: Stantec H2O+U - UK.
About You
We are interested in speaking with passionate engineers with design experience within the UK water industry. You’ll hold a degree in Civil Engineering and ideally have achieved Chartered status with a relevant professional body such as ICE or CIWEM. You will have gained experienced delivering community focused projects, whilst working collaboratively with multi-disciplinary teams to delivery innovative solutions. We will support your growth & development through training & project exposure, though prior experience within storm overflows, SUDS, surface water management & sewage treatment would be beneficial.
About Stantec
The Stantec community unites more than 31,000 employees working in over 450 locations across 6 continents. We have been working with our clients and communities in the UK for over 150 years. We plan, design, deliver and manage the development and infrastructure needed to support the creation of sustainable, healthy and prosperous communities. Our teams provide effective and relevant solutions, translating our clients’ vision into valued consents, deliverable plans for projects and programmes, and efficient designs for delivery, based on technical excellence and deep market insights. We deal with today’s challenges, but also keep a fairer, better tomorrow in sight, looking at how we deliver clean growth, support radical changes in our economy and meet the needs of future communities. Stantec provides equal employment opportunities to all qualified employees and applicants for future and current employment and prohibit discrimination on the grounds of race, colour, religion, sex, national origin, age, marital status, genetic information, disability, sexual orientation, gender identity or gender expression. We prohibit discrimination in decisions concerning recruitment, hiring, referral, promotion, compensation, fringe benefits, job training, terminations or any other condition of employment. Stantec is in compliance with laws and regulations and ensures equitable opportunities in all aspects of employment. Building an inspired, inclusive work environment that attracts, supports, and develops world-class talent is a crucial key to our success. If you are excited by this role but worry that your experience doesn’t exactly align, we encourage you to apply.