Supply Chain - Sewerage - Products
- Arklow Long Sea Outfall (2023)
- Potters Way Sewer Rehabilitation (2023)
- Exmouth Offshore Project (2024)
- Ballygowan WwTW (2023)
- WINEP Durham Transfers (2024)
- Ards North Long Sea Outfall (2023)
- Esholt STW (2024)
- Sherston S101a - First Time Sewerage Scheme (2023)
- Chilton Foliat STW Flow Compliance (2023)
- Raigersfeld Culvert Re-lining
Raigersfeld Culvert Re-liningKent County Council‘s programme of planned highways maintenance works to be carried out during 2019 – 2021 included strengthening works to structures such as the Raigersfeld Culvert situated beneath the A20 Ashford Road, Maidstone, Kent. Following on from previous culvert rehabilitation works for Kent County Council, Steadline Ltd. were once again commissioned to make the required improvements to an existing historical brick and steel beamed culvert which was showing signs of deterioration resulting the restriction of flow capacity. With the same project team comprising Steadline Ltd., BdR (Civil & Structural Engineering) Ltd. and Amiblu, a bespoke, non-circular GRP liner was designed with specific challenges to overcome, including:
- Steel cross sections to the soffit of the culvert
- Inconsistent shape
- Traffic loads
- Restricted access
- Environmental considerations
Project parameters
- Country: UK
- City: Maidstone
- Year of construction: 2021
- Application: Storm sewer
- Installation: Trenchless
- Technology: Amiblu NC Line
- Total length of pipe: 16m
- Nominal diameter DN: 1244mm x 754mm
- Nominal pressure PN (bar): PN1
- NC Line shape: Elliptical (1m lengths)
Supply chain
- Client: Kent County Council
- Contractor: Steadline Ltd
- Engineer: BdR (Civil & Structural Engineering) Ltd
- NC Line relining pipe: Amiblu
What was said
Aaron Harber, Contracts Manager, Steadline Ltd.” All in all the scheme was very successful and certainly improved the flow of the stream/small river and with the new rag stone head walls looked very pleasing to the eye.”
For more information: Amiblu UK | +44 (0)7786 013574 | www.amiblu.com
- Gipsy Patch Lane (Bristol) Sewer Rehabilitation
Gipsy Patch Lane (Bristol) Sewer Reh...Gipsy Patch Lane, Bristol is a main road forming part of a new Cribbs Patchway Metrobus route in South Gloucestershire. As part of an asset assesment programme a few years ago, a CCTV survey showed many defects throughout the length of the surface water culvert at Gipsy Patch Lane. The defective sections ran under the busy carriageway so, as an interim maintenance measure the local authority excavated a section of the road and installed a concrete slab over the pipe to protect it from further deterioration or collapse. During heavy rainfall over the summer of 2020, the same pipe was found to have suffered structural defects and root ingress through open joints and connecting laterals resulting in localised blockages of up to 90%. A new man-entry survey showed the pipe beneath the concrete slab to be deformed. Major works were already under way in the area to replace a railway bridge on Gipsy Patch Lane, so South Gloucestershire Council took the opportunity to make improvements to the sewer in conjunction with the Network Rail works to minimise disruption, which was further aided by lighter traffic due to the regulations set in place for Covid-19 pandemic. Under the Council’s Climate Resilient Scheme, the task was to find and deliver a suitable solution before opening the road up to traffic and risking a pipe collapse; two options were considered; open-cut to replace the section of pipe or trenchless technology to reline the affected pipe with little disruption to the area. [caption id="" align="alignnone" width="1200"] First post-Brexit delivery of Amiblu pipes (January 2021)[/caption] Doug MacKay, Project manager, South Gloucestershire Council consulted with Julian Britton, Critical Sewers Manager, Wessex Water and Matt Durbin Associates; specialist confined space and GRP structural relining installer to determine the most efficient and economic technique. As with many suburban roads, Gipsy Patch Lane is laden with many services within the carriageway, so rehabiliatation of the existing pipeline through trenchless installation of 210m x DN800 structural GRP jacking pipe supplied by Amiblu was decided upon. As the contract was classed as emergency works, subject to time constraints and speed of execution the use of Amiblu’s GRP pipes meant that MDA were able to remove the need for costly over-pumping and install the pipes in live flows, whilst minimising their work area to a single lane closure for uninterupted access to local businesses. During the installation of the initial contracted 210m, a further 70m section of the pipe downstream required attention, so MDA undertook the additional works saving additional costs and disruption at a later date. Amiblu jacking pipes are often utilised in pipe rehabilitation projects such as this as they offer a high compressive strength and, compared with conventional materials, an improved hydraulic coefficient. The hydraulic analysis carried out for Gipsy Patch Lane showed no reduction in hydraulic performance and as the pipes are designed to offer a service life in excess of 150 years with minimal maintenance, the life expectancy of this asset is greatly improved. [caption id="" align="alignnone" width="1200"] (left) GRP pipe installation and (right) the completed relining - Courtesy of MDA Ltd[/caption] Doug MacKay, Project Manager with South Gloucestershire Council, commented:
"For this project, the Council had concerns about the risk of potential pipe collapse under traffic loading. The fact that road was already under a full closure due to an adjacent project to replace an old railway bridge meant that timing was critical for this project. It was essential that the work had to be completed before the proposed re-opening of the carriageway. Additionally, there was a limit to the funds available through the Climate Resilience budget to complete the scheme. We worked very closely with MDA and our designers to review the site constraints, risks to programme delivery and budget constraints to determine the most appropriate remedial solution. I was grateful for the time, input and patience spent by MDA during this period to explain the construction process and provide answers to all our questions and concerns in advance of making the final decision on the preferred option.
Once the decision was made to proceed with the pipe-jacking option the process was relatively straight-forward and stress-free from the Council side of things. In the main this was down to the excellent communication, planning and execution of the works by MDA. Both projects were completed on-time, within budget and with minimal disruption to the public and businesses that rely on using Gipsy Patch Lane.”
[caption id="" align="alignnone" width="1200"] Amiblu pipes require minimal site storage - Courtesy of MDA Ltd[/caption]Project details
- Country / city: UK, Bristol
- Year of construction: 2021
- Installation time: 4 weeks
- Application: Sewer rehabilitation
- Installation: Trenchless technology
- Technology: Hobas
- Total length of pipe: 280m
- Nominal diameter DN (mm): DN800
- Nominal pressure PN (bar): PN1
- Nominal stiffness SN (N/mm²): 32,000
Supply chain
- Client: South Gloucester Council
- Contractor: Matt Durbin Associates Ltd
- Consulting engineer: South Gloucester Council
- Structural GRP jacking pipe: Amiblu
Amiblu Structural Relining Pipes
Amiblu pipes have a smooth, resin rich internal surface with high abrasion resistance which consistently prevents fouling and build up, leading to low maintenance costs and high flow rates even at low gradients. Both Jacking and relining pipes are supplied with in-line flush joints which prevent the intrusion of roots and further ensure the integrity of the asset. Available in diameters from DN300 to DN3600, in varying strengths and lengths. Amiblu’s systems are cost effect, durable alternatives to traditional pipe systems.
For more information: Amiblu UK | +44 (0)7786 013574 | www.amiblu.com
- East Budleigh Culvert Re-lining
East Budleigh Culvert Re-liningEast Budleigh is a small village in East Devon, UK located about 2 miles (3.2km) north of Budleigh Salterton. The village features a bypass culvert, constructed in the 1970s. The culvert is approximately 280 metres in length, of Armco construction, oval shaped and constructed from corrugated metal sheeting (with a concrete floor laid over it during the last 10 years). The existing culvert was in a poor condition, with joints failing and large voids appearing in the material outside the culvert structure. These failures led to a small localised collapse in the road above during flooding in 2012 and there were concerns that in the future that a larger collapse could occur, causing a failure in the highway surface. It was decided that this culvert required structural strengthening due to minimal cover to the busy road above, and to maintain flows through the culvert in storm conditions. [caption id="" align="alignnone" width="1200"] (left) Host pipe inspection and (right) site preparation - Courtesy of MDA Ltd[/caption]
Project scope
The Environment Agency employed Atkins to design the culvert rehabilitation, with Kier appointed as main contractor who in turn appointed specialist contractor Matt Durbin Associates to consult on rehabilitation options and carry out the work. Given that the location was a highly trafficked residential area with minimum cover to the road, it was decided that lining with a structural GRP segment lining system offered the best solution and Amiblu‘s NC Line, non-circular GRP Structural Relining system was selected for the project. In total some 300 metres of Amiblu NC Line Arch Shape liner, 2360mm wide x 1350mm high was manufactured to the required WRC Type II standard and ISO 16611. Amiblu’s application engineers worked in partnership with Matt Durbin Associates to understand specific performance criteria required in order to create the optimal shaped pipe to fit the needs of the project and production started in January 2022 at Amiblu’s Gdansk factory in readiness to commence February deliveries. The culvert meandered with the local water course, and on inspection for the design of the linings was found to include long radius bends which were designed for pre-manufacture so that they would install without issue on site. Despite the apparent loss of cross-section in the culvert the design and smooth internal finish of the linings ensured that the flow capacity requirements for the culvert would be met. Given the small village size and the traffic management requirements for the installation works, coordination with local residents and parish councils regarding the large deliveries to site was essential and worked extremely well. [caption id="" align="alignnone" width="1200"] Amiblu NC Line 2360 x1350mm ready for installation[/caption] Work commenced on site on 14 February with site preparation works. Installation into the culvert commenced in March. In total, all installation and annulus grouting operations were completed in just 8 weeks. Amiblu’s NC Line provides structural rehabilitation to existing non- circular culverts and host pipes that have reached a point in their service life where the asset owner must decide to renovate or replace. GRP pipe systems made by Amiblu maintain excellent long-term stiffness, corrosion and abrasion resistance and are engineered for 150 years‘ service life.Project parameters
- Country: UK
- City: East Budleigh
- Year: 2022
- Application: Culvert reline
- Installation: Trenchless
- Technology: Amiblu NC Line
- Total length of pipe: 300m
- Nominal Diameter DN (mm): 2360 x 1350mm
- Nominal Pressure PN (bar): PN1
- Nominal Stiffness SN (N/mm2): As per design criteria
Supply chain
- Client: Environment Agency
- Contractor: Matt Durbin Associates Ltd
- Consulting engineer: Atkins
- Structural GRP pipe liner: Amiblu
What they said
Daniel Gay, Project Manager for the Environment Agency:“From a client perspective, the GRP liner solution has provided a cost and time-effective approach to prolonging the asset life. We were hopeful to avoid any requirement for open cut solutions to minimise the impact to the local community and meet delivery deadlines. We also needed to ensure that the flood risk standard of protection was not altered to upstream or downstream receptors. The structural GRP liner allowed for a bespoke unit to be installed which optimised the culvert capacity to retain the flow performance and extended the life. The outcome of improvements to the culvert have reduced flood risk to 27 residential properties, significantly reduced future maintenance costs and health and safety risks to the public.”
Adrian Parker, Senior Project Manager, Kier:“This project is a great example of how accelerated delivery can be achieved under the Environment Agency’s Collaborative Delivery Framework. From identification of the scheme for fast tracking in June 2021, the scheme was on the ground in February 22 and complete by June 22. MDA have done a great job and thanks also to Amiblu.”
For more information: Amiblu UK | +44 (0)7786 013574 | www.amiblu.com